Tram Road Reopened 10 Days Ahead of Schedule

Tallahassee - The following is an update on construction activities for the Capital Circle Southeast (Tram Road to Connie Drive) roadway improvement project. Due to good weather and a strong effort by the project construction team, the intersection of Tram Road from east of Capital Circle to Four Oaks Boulevard has reopened 10 days ahead of schedule.

Construction of the $36 million project began in May 2005 and is scheduled to finish in early 2008. However, weather, underground utility conflicts or other unforeseen circumstances could delay or prolong construction activities.

Download a PDF version of this press release (26KB)

 


Blueprint2000.org · 1311 Executive Center Drive, Suite 109 · The Koger Center, Ellis Building
Tallahassee, FL 32301 · Tel: 850.891.1880 Fax: 850.891.1885

   
View CCSE Project Map View Project Timeline View CCSE Project Map View Project Timeline