The week of July 12 through July 19, 2005.
Utility Relocation crews in progress for (Gas, Electric, and Telephone):

* Pole locations for the City power have been staked and the crews are laying out the material.
1 Relocation crews pulled off for Hurricane work until later in the week.
2 City Gas is planning to put stub outs at the Merchants Row and Shumard Oak intersections. The crew is waiting on the alterations made in drainage and erosion control before making the final mark-ups.
3 Telephone relocation crews will continue boring North till the end of project. A temporary drop wire will be installed at the FAA site, until there is resolution to bore on their site. Boring crew should be completed next week with the exception of the FAA site.

 

   
   
   
   
   