Home Traffic Updates Project Photos F.A.Q. Contact Us

FOR IMMEDITAE RELEASE
June 30, 2005

CONTACT:
Carlana Hoffman
Public Information Officer
hoffmanc@blueprint2000.org

Bonnie Pfuntner
Public Involvement Manager
pfuntneb@blueprint2000.org

Capital Circle Southeast Construction Progress Update

(Tram Road to Connie Drive) - The week of June 28 through July 12, 2005.

1. Crews will be working on embankment work on the roadway, west side, south of Merchants Row. This work will not have impact on traffic flow.
2. Excavation for Pond 4W is in progress; Pond 3 excavation has been halted due to lack of fill areas.
Utility Relocation crew in progress for (Gas, Electric, and Telephone).
• Pole locations for the City power have been staked. The relocation crew is ready to start next week.
• City Gas planning to put stubs outs at the Merchants Row and Shumard Oak intersection.
• Sprint relocation crew will continue North till the end of the project. A temporary drop wire will be installed for relocation purposes.

Maintenance Of Traffic Issues
• Grade at Blairstone will be lowered by 2’.

Blueprint2000.org · 1311 Executive Center Drive, Suite 109 · The Koger Center, Ellis Building
Tallahassee, FL 32301 · Tel: 850.891.1880 Fax: 850.891.1885

   
View CCSE Project Map View Project Timeline View CCSE Project Map View Project Timeline