Capital Circle Southeast Construction Progress Update
(Tram Road to Barcelona Lane) - The week of October 12, 2005
The Design/Build team has obtained a conditional fill placement permit for Segment 2, from just north of Tram Road to Barcelona Lane from the City of Tallahassee (COT) and the Department of Environmental Protection (DEP).
* Crews are clearing and installing erosion control measures on
Segment 2.
* Fill placement will commence shortly on this project.
Maintenance Of Traffic (MOT) and Erosion Control Activities are ongoing.
|